Tesla unveils Oasis: a brand new Supercharger idea with its personal photo voltaic farm and Megapacks


Tesla has unveiled plans for a brand new Supercharger mission known as ‘Oasis’, which is able to embody 168 Superchargers mixed with its personal photo voltaic farm and Megapack battery system.

Early within the deployment of the Supercharger community, Tesla promised so as to add photo voltaic arrays and batteries to the Supercharger stations, and CEO Elon Musk even mentioned that the majority stations would be capable of function off-grid.

Whereas Tesla did add photo voltaic and batteries to a couple stations, the overwhelming majority of them don’t have their very own energy system or have solely minimal photo voltaic canopies.

Again in 2016, I requested Musk about this, and he mentioned that it could now occur as Tesla had the “items now in place” with Supercharger V3, Powerpack V2, and SolarCity:

Effectively, we now have Supercharger V4, Megapack, and SolarCity, which have been absorbed after which mainly rejected by Tesla, and but, we nonetheless have restricted photo voltaic and battery deployment at Superchargers.

Earlier this yr, we reported on a deliberate Supercharger mission in Misplaced Hills, California, that we mentioned may give us “a glimpse at the way forward for charging” resulting from the usage of photo voltaic, a microgrid, and a number of other pull-through charging stalls for vans.

Tesla has now unveiled the mission known as ‘Oasis’ on Interstate 5 between Los Angeles and the Bay Space. Right here’s a render of the mission:

Max de Zegher, Tesla’s head of charging, launched some particulars of the mission:

  • 168 stall Supercharger in Misplaced Hills, CA
  • Just one.5 MW grid service, forward of a future enlargement
  • 11 MW of floor mount photo voltaic and canopies, on 30 acres of land
  • 10 Tesla Megapacks with 39 MWh of storage

The principle function right here is the massive 11 MW photo voltaic capability mixed with 39 MWh of Megapack storage capability, which permits Tesla to have a minimal grid connection.

Tesla has damaged floor for the mission:

de Zegher explains the necessity to go partly off-grid:

We’re working in lockstep with the utility, however resulting from native substation improve timelines, we’d not have been capable of meet 2025 charging demand. Though we’re sometimes grid related, on this case, we’re leveraging the total Tesla ecosystem and our vertical integration.

Nevertheless, Tesla remains to be planning so as to add extra grid capability at this web site if there’s a necessity to extend the variety of stations. de Zegher says that Tesla is ready to double the capability.

Electrek’s Take

That is superior. It’s nearly a decade after Musk mentioned it could occur, however it’s nonetheless superior.

Earlier than Musk followers use this to justify firing the whole charging workforce (and hiring again lots of them), because it’s now occurring after that, now we have recognized about this mission since February, which was earlier than the workforce was fired.

So, the brand new workforce merely continues the mission began by the earlier workforce.

Tesla’s Supercharger deployment has gone down this yr each on the variety of stations and the variety of stalls, however it’s nonetheless rising and lately hit the 60,000th Supercharger milestone globally.